General Building Information

Building Name

Location and Site

Occupant Name

Occupancy

Size

Number of Stories

Dates of Construction

Cost Information

Delivery Method

Remington Row

Baltimore, MD

Remington Row

Mixed Use

245,145 SF

5 Stories

January 2015 - August 2016

$26 million (construction cost)

Design - bid - build

​

Project Team

Architect

General Contractor

Structural Engineer

MEP Engineer

Civil Engineer

Landscape Architect

Interior Designer

Lighting Designer

Client

Building Statistics

General Building Information

Building Name

Location and Site

Occupant Name

Occupancy

Size

Number of Stories

Dates of Construction

Cost Information

Delivery Method

Remington Row

Baltimore, MD

Remington Row

Mixed Use

245,145 SF

5 Stories

January 2015 - August 2016

$26 million (construction cost)

Design - bid - build

​

Project Team

Architect

General Contractor

Structural Engineer

MEP Engineer

Civil Engineer

Landscape Architect

Interior Designer

Lighting Designer

Client

CPEP Site Complete and Ready for Final Review

​

Final Presentation Uploaded

 

Final Report Uploaded

​

CPEP Updated​

​

Proposal Posted

​

Notebook Submission C Posted

​

Building Statistics Part 2 Posted

​

5/6/2021

 

 

4/30/2021

 

 

4/30/2021

​

12/14/2020

​

12/11/2020

​

11/18/2020

​

​

8/26/2020

​

Notebook Submission B Posted

​

Notebook Submission A Posted​

​

Structural Existing Conditions  Report Posted

​

Projects Specs Obtained

​

Initiation Checklist Part 1 Turned In

​

Thank you email sent

​

Owner permission form received

​

Project drawings obtained

 

Owner approval received

​

10/30/2021

 

10/24/2020

​

10/5/2020

​

​

9/16/2020

​

8/24/2020

​

8/19/2020

​

8/19/2020

​

8/3/2020

​

8/3/2020

Note

While great efforts have been taken to provide accurate and complete information on the pages of CPEP, please be aware that the information contained herewith is considered a work-in progress for this thesis project. Modifications and changes related to the original building designs and construction methodologies for this senior thesis project are solely the interpretation of Musaed Alhajeri. Changes and discrepancies in no way imply that the original design contained errors or was flawed. Differing assumptions, code references, requirements, and methodologies have been incorporated into this thesis project; therefore, investigation results may vary from the original design.